All American Track Inc. is a railroad services company that provides railway construction, maintenance, and repair with utmost safety, quality, and value. With decades of industry experience and national accreditations, we are a trusted authority in the business. Our work is always completed to exceed our customer’s expectations.

BRIGHTLINE

HSR CONTRACT
2022/2023
OVERVIEW

New track construction adjacent to existing track and commercial rail operations. Replaced under-performing contractor to finish the project within the two-year time limit. Total project is among the largest rail construction projects in the world.

TASKED TO DESIGN AND BUILD

• 101 m of High-Speed Track Construction
• 40 Turnout Construction
• 25 km of Class 7 Track Surfacing
• Removed and reinstalled track across
(10) bridges and (18) crossings

CANADIAN PACIFIC RAILWAY​

QUAD CITIES TIE REPLACEMENT PROGRAM
2019
OVERVIEW​

Large-scale maintenance initiative over an extended period. Challenging weather (flooding) required emergency track repair. Project demanded a realignment of the existing track to a new higher demand and track utilization.

TASKED TO DESIGN AND BUILD

• 124,742 Cross-ties Installed
• 159 km Stabilize, Surface, Align and Dress Track
• 131 Road Crossing Rehabilitations
• Absolute Cleanup Within Program Limits, Including Legacy Ties

All American Track is a railroad services company that provides railway construction, maintenance, and repair with utmost safety, quality, and value. With decades of industry experience and national accreditations, we are a trusted authority in the business. Our work is always completed to exceed our customer’s expectations

KANSAS CITY SOUTHERN RAILWAY

ROADHOUSE TIE REPLACEMENT PROGRAM
2019
OVERVIEW

High-profile track maintenance project with an accelerated completion schedule. Formed and deployed a high-performance mega rail maintenance crew on short notice and completed the project on time and on budget.

TASKED TO DESIGN AND BUILD

• 55,000 Cross-ties Installed
• 93 km Stabilize, Surface, Align, and Dress Track
• Rehab and Replace Road Crossings Throughout
• Large Production Crew

ARIZONA EASTERN RAILWAY​

FMI SUMMIT YARD PROJECT​
2022/2023
OVERVIEW

New construction rail yard in western New Mexico. Tasked to design, engineer, and build on unimproved land adjacent to a local ranch in a remote location with no infrastructure or resources, and significant environmental and ecological sensitivities. Total engineering and construction timeline of eight months.

TASKED TO DESIGN AND BUILD

• 7,813 m of New Railroad Construction
• 671 Flash-butt Welds
• 7 Turnouts Constructed and Installed